.................is the part of building constructed above the plinth level.
Superstructure
Substructure
Foundation
Plinth
126 practice sets · Page 1 of 7
.................is the part of building constructed above the plinth level.
Superstructure
Substructure
Foundation
Plinth
.................is the unit of measurement of intensity of light?
1 lux – 5luman/m2
1 lux – 1luman/m2
1 lux – 10luman/m2
2 lux – 6luman/m2
................consists of driving either a hollow tube or a steel rod or an iron rod into the ground.
Trail pits
Test piles
Probing
Digging
...............consist of a vibrating unit mounted on a screed, plate or roller.
Earth rammers
Pounding
Vibrating rollers
Vibratory compactors
..............are the most commonly used equipment for transportation.
Dump trucks
Rollers
Trucks
Bulldozers
..............is a process of connecting cables & wires to the related devices such as fuse switches, lights, fans etc to the main distribution board for continuous power supply.
Electric wiring
Water supply
Both a and b are correct
Both a and b are not correct
..............is a wooden material made artifically from solid wastes like sawdust, flyash and other biodegradable wastes etc.
Artifical Timber
Wall Cladding
Acoustic Material
None of the above
..............is the practice of assembling components of a structure in a factory or other manufacturing site, and transporting complete assemblies or sub-assemblies to the construction site where the structure is to be located.
fabrication
Prefabrication
Damping
Scaffolding
..............is the process in which we cover the structural members of a building to increase the strength of the building.
Jacketing
scaffoldings
Shoring
Sesmic Retrofitting
.............are structural members design to carry and transfer transverse loads across space to support elements.
Beams
Columns
Lintels
Sills
.............is a flexible material which is commonly used for the damp proofing.
Hot bitumen
Bituminous felts
Mastic asphalt
Metal sheets
.............type of excavator is used for digging at or below the operating level.
Skimmer
Dragline
Power shovel
Dredger
.............wall is constructed in order to support load other than its own.
Load supporting
Load distributing
Load bearing
Load releasing
............equipment are used to decrease the porosity of earth and to increase the density and strength of the earth.
Excavation
Compaction
Hauling
Hoisting
............is a self propelled machine which is used mainly to exert a powerful tractive force for pulling other machines.
Tractor
Bulldozer
Angle dozer
Scraper
..........is very useful equipment and it can be used for construction work like to clear the site of work, to make the land level, etc.
Scraper
Grader
Excavator
Bulldozer
.........is the top most part of building which provides covering to the entire assembly and the occupants.
Roof
Ceiling
Coping
Parapet wall
A building that does not have symmetry & plan, elevation, geometry mass on load is called
irregular building
regular building
None of these
All of these
A city supply includes
Domestic water demand
Industrial and commercial water demands
Demand for public uses and fire
All the above
A square pit, known as................with side as about 1.50 m, is excavated upto a depth at which sufficiently hard soil is available.
Test pits
Probing
Test piles
Deep boring